• 01.07.2012 - 22.08.2012

    IDMC Overseas FZE, Sharjah, UAE

    FPSO Chain Recovery & Inspection and SBM hose replacement at offshore Rospo Mare Oil Field Italy

  • 05.07.2012 - 18.08.2012

    LIN SCAN, Hamriyah Free Zone, Phase – I, Sharjah

    30” Gas Pipeline Repair – Removal of Pig by 8” hot tapping and installation of Flanges

  • 04.10.2012 - 25.10.2012

    Maersk Oil Qatar

    Subsea commissioning support

  • 14.11.2012 - 18.12.2012

    PBJV Group Sdn Bhd

    Provision Diving and Pipeline Pre-commissioning Services for KPOC Pipeline 2012 Campaign Project – 14” Pipeline x 123 km & 24” Pipeline x 123 km from KBB to SOGT

  • 13.10.2013 - 07.03.2014

    Impresub Diving and Marine Contractor

    Spool Piece Installation at Al Basrah Oil Terminal

  • 06.08.2013 - 21.12.2013

    Sapura Kencana / Allied Marine and Equipment

    BPI of process platform KNPG – B in Offshore Labuan, Malaysia

  • 05.08.2013 - 05.10.2013

    Maersk Oil Qatar

    Heavy Lift Operation

  • 21.03.2013 - 28.07.2013

    Shell Singapore / Leighton

    Dive Support during replacement of Bukom Refinery Pipeline

  • 22.02.2013 - 29.03.2013

    ADDAX Petroleum / Kaztec

    (1)Saturation, Air Diving and ROV, OK-16 GL Umbilical Swivel Flange – close visual inspection (CVI) of GL umbilical swivel flange & check tightness of flange and leak rectification (2) OK-7 GL Umbilical SUTU-lift the GL umbilical SUTU on DSV for investigation & repair (3) Revisit OK-16 GL umbilical swivel flange – WROV to check & monitor OK-16 GL umbilical swivel flange for leaks

  • 07.04.2014 - 08.10.2014

    New Wing Energy Offshore / Murphy Oil

    Offshore Support Duties at Kikeh Field, Malaysia

  • 03.07.2014 - 02.10.2014

    Rana Diving S.P.A / Saipem - ENI

    Installation of Riser, Tie-ins and Free Span Correction for the Ellettra and Fauzia Platforms in Italy.

  • 31.03.2014 - 15.06.2014

    Sapura Kencana / Allied Marine and Equipment

    IMR Campaign – Saturation/ Air Diving at Malaysia Offshore

  • 27.05.2014 - 04.06.2014

    Boskalis Offhore Subsea Services Middle East.

    Rectification of pipeline leak

  • 29.01.2014 - 12.03.2014

    Undine Marine Industries (UMI)

    Air Diver for Hot Tapping on the sunken ship’s Oil Tank to remove all the Oil from the ship’s tank at Oman Offshore

  • 01.12.2014 - 22.07.2015

    Saipem Eni / South Stream

    Assist and support pumping operations and ROV intervention required for AFT functioning over Subsea Initiation Head at Russian end for the Southstream project

  • 13.10.2014 - 31.03.2015

    Technip Abu Dhabi/ Dubai Petroleum

    Grouting Operations, Freespan Correction, Installation of Crossings, Risers and Spool piece Installation associated with the Jalilah B field development project owned by Dubai Petroleum

  • 16.11.2014 - 04.02.2015

    Technip Abu Dhabi/ Dubai Petroleum

    Riser and Spool Piece Installation associated with the Jalilah B field development project owned by Dubai Petroleum

  • 24.04.2016 - 30.05.2016

    Leighton Offshore PTE. LTD.

    Air Diving and ROV Services for Subsea Asset Inspection inclusive of 48” Pipeline Inspections and SPM 4 Anchor Spread Inspection

  • 28.10.2015 – 08.03.2016

    Saudi Aramco / Snamprogetti - ENI

    Construction Support on Marjan and Zuluf Field, Saudi Aramco

  • 14.07.2015 - 27.10.2015

    Saudi Aramco / Snamprogetti - ENI

    ROV and Construction Support Pipeline demobilisation, laying of mattresses and installation of alignment frames on Marjan and Zuluf Field, Saudi Aramco

  • 10.09.2015 - 08.10.2015

    Maersk Oil Qatar

    Offshore Support as Accommodation Vessel for Personnel working on the Platforms in the Al-Shaheen Field

  • 18.04.2012 - 05.06.2012

    COOEC /All-Sea Offshore Asia Ltd.

    Panyu Field Adjustment Project, Saturation Diving, Subsea construction & installation

  • 25.04.2012 - 16.05.2012

    Smit Subsea Middle East LLC, Dubai | Dubai Petroleum Establishment, Dubai

    Excavation mud around 30” pipeline leak location and cutting the pipe on four locations. Removing old pipe in three pieces, install 30” smart flange on old pipe cut end. Installation of two Spool Piece in between smart flanges.

  • 20.02.2012 - 14.04.2012

    Cairn Energy India Pvt. Ltd

    Inspection of Platform Jackets Recertification at Ravva Field

  • 19.02.2012 - 05.03.2012

    Leighton Offshore, Dubai

    48” Spool Piece Installation on SBM1, SBM2 and SBM3 / Cable Lay Persian Gulf

  • 13.12.2011 - 11.02.2012

    Leighton Offshore, Dubai/ Ocean King Surveys, Sharjah

    48” Spool Piece Installation on SBM1, SBM2 and SBM3, Persian Gulf

  • 25.04.2016 - 07.06.2016

    UMI / LS Cable & System Ltd / Qatar Petroleum

    Air Diving Operations for Tekspace remedial and grout bag installation for designated pipeline crossings.

  • 27.06.2016 - 10.08.2016

    PBJV

    1.Pipeline Pre-commissioning Work 2.Riser Installation 3.TIe-in Spool Piece Installation 4.Knee-brace Removal 5.Pipeline Post Installation Works and Survey 6.Pipeline Crossings and Supports (using ROV)

  • 05.07.2016 - 16.08.2016

    ROV Resources (M) SDN BHD

    Completion for the underwater inspection for 5 nos. of platforms, 9 nos. of pipeline, 17 nos. of riser, 3 nos. of plet, 2 nos. of fibre optic cable, 2 nos. mid water arch – using SAT diving, Air diving, work class ROV (swift), Inspection ROV (Comanche) & online underwater inspection.

  • 18.09.2016 - 23.11.2016

    PBJV

    1.Pipeline Pre-commissioning Work 2.Riser Installation 3.Tie-in Spool Piece Installation 4.Knee-brace Removal 5.Pipeline Post Installation Works and Survey 6.Pipeline Crossings and Supports (using ROV)

  • 14.04.2016 - 18.05.2016

    BG Exploration Production India Limited

    Air Diving Support for SBM Activities in Panna Mukta Fields, India

  • 08.10.2009 - 25.05.2010

    UDPL/ONGC, Mumbai

    Charter Hire of Saturation Diving System – Sat Dhruv

  • 06.10.2007 - 20.05.2008

    HAL Offshore, Mumbai, India

    I.M.R. Program at ONGC Bombay High Fields – Supply of Personnel

  • 31.08.2016 - 27.09.2016

    Sapura Kencana Petroleum Berhad

    MOPU Sepat legs (2 Nos) were cracked same were clamped and welding was carried out as required. ROV survey of all 3 legs of MOPU Sepat

  • 03.10.2016 - 23.11.2016

    Sapura Kencana Petroleum Berhad

    MOPU Sepat legs (2 Nos) were cracked same were clamped and welding was carried out as required. ROV survey of all 3 legs of MOPU Sepat

  • 15.03.2016 - Ongoing

    BG Exploration Production India Limited

    Air Diving Support for SBM Activities in Panna Mukta Fields, India

  • 17.02.2017 - 18.03.2017

    DSV Altus Optimus

    Re-installation of SPM 5 buoy and marine services at Al Basrah Terminal, Iraq

  • 03.04.2017 – 12.04.2017

    BG Exploration Production India Limited / Shell

    Altus Invictus-Air Diving Services for Riser Inspection, MGR and Riser Guard Inspection.

  • 24.02.2017 – 25.03.2017

    BG Exploration Production India Limited / Shell

    Altus Invictus-Air Diving Services for Fabrication & Installation & Hydro testing of Sectional Spool (Subsea and Topside) on 1 x Riser with Oceaneering Smart Connector (Riser Remediation Project) in Panna Mukta Fields, India.

  • 24.02.2017 – 10.03.2017

    BG Exploration Production India Limited / Shell

    Jaya Vigilant-Air Diving Services for Installation of Sectional Spool on 1 x Riser with Oceaneering Smart Connector (Riser Remediation Project) in Panna Mukta Fields, India

  • 14.04.2017 – 25.05.2017

    BG Exploration Production India Limited / Shell

    MMA Pinnacle-1) Field joint inspection on 18" sales export pipeline 2) Annual inspection & maintenance of Panna SPM 3) Inspection of PPA 18" Riser with Spool piece 4)Riser inspection of 10" PB-PA & 4" PPA-PB at PB platform 5) Riser inspection of 6"PA-PD, 12" PA-SPM, 10" PE-PA riser